Question 11

Q11) A, B and C together finish work in 4 days. If A alone can finish the same work in 8 days and B in 12 days, find how long it will C take to finish the work.

Solution:

A, B and C finish work together in = 4 days

A,B and C finish work together in 1 day = \frac{1}{4}

A’s one day work = \frac{1}{8}

B’s one day work = \frac{1}{12}

∴ C’s one day work = \frac{1}{4}-[\frac{1}{8}+\frac{1}{12}]=\frac{6-(3+2)}{24}=\frac{1}{24}

∴ C can finish the work in = 24 days

Still have questions? Our expert teachers can help you out

Book a free class now

Want to top your mathematics exam ?

Learn from an expert tutor.

Book a free class now
subject-cta
linkedin instgram facebook youtube
2020 © Quality Tutorials Pvt Ltd All rights reserved
linkedin instgram facebook youtube