Ml aggarwal solutions
Our top 5% students will be awarded a special scholarship to Lido.

Direct and Inverse Variation | Direct and Inverse Variation Exercise 9.3

Question 11

A, B, and C working together can plogh a field in 4 4/5 days. A and C together can do it in 8 days. How long would B working alone take to plough the field?

Looking to do well in your science exam ?  
Learn from an expert tutor. Book a free class!

Given:

(A + B + C) can plough a field in = 4 4/5 days = 24/5 days

(A + B + C)’s 1 day work = 5/24 days

(A + C) can plough a field in = 8 days

(A + C)’s 1 day work = 1/8 days

B’s 1 day work = (5/24) – 1/8

= (5-3)/24

= 2/24

= 1/12

∴ B can do the work in 12 days

Set your child up for success with Lido, book a class today!

Our top 5% students will be awarded a special scholarship to Lido.

subject-cta

Question 11

A, B, and C working together can plogh a field in 4 4/5 days. A and C together can do it in 8 days. How long would B working alone take to plough the field?

Looking to do well in your science exam ? Learn from an expert tutor. Book a free class!

Given:

(A + B + C) can plough a field in = 4 4/5 days = 24/5 days

(A + B + C)’s 1 day work = 5/24 days

(A + C) can plough a field in = 8 days

(A + C)’s 1 day work = 1/8 days

B’s 1 day work = (5/24) – 1/8

= (5-3)/24

= 2/24

= 1/12

∴ B can do the work in 12 days